High risk
  • Possession delayed ~9 yrs. Originally promised Sept 2019, now proposed Apr 2028 per the RERA filing.
  • High complaint rate. 5 complaints against only 11 sold units — a high rate for a project this size.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · 48/4A AT SHIVAJI NAGAR, Shivaji Nagar

Area guide

What it's like to buy in Shivaji Nagar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Pride Construction and Infrastructure Limited

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004910
Status
Ongoing
Stage
Certificate Signed
Possession
April 2028originally September 2019
Construction
68.2% complete
Units sold
11 of 56

Similar projects in Shivaji Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Shivaji Nagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.