High risk
  • Possession delayed ~3 yrs. Originally promised Feb 2019, now proposed Apr 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · gat no 1307/pt , gat no 1314, Palghar

Promoter

Builder profile

Builder
Empire Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000003256
Status
Ongoing
Stage
Certificate Signed
Possession
April 2022originally February 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Palghar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Palghar compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.