Dhoot Sky Residency-New Sonali CHSL
CTS NO 307/105 AND 307/107, Malad West, 400064
- Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 54.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · CTS NO 307/105 AND 307/107, Malad West
Area guide
What it's like to buy in Malad West
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Retail-and-BPO hub with dense mid-income housing on both sides.
- Growth drivers:
- Mindspace offices, Link Road retail, Metro 2A.
- Who buys here:
- Mid-income families, first-time buyers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800008715
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2022originally June 2021
- Construction
- 54.1% complete
- Units sold
- 0 of 0
Similar projects in Malad West
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Malad West compares.
In Malad West
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.