High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 31.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · 48, Sativali

Area guide

What it's like to buy in Sativali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
M/s Dias Properties & Projects

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000007801
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally June 2021
Construction
31.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Sativali compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.