Dias Residency Park
by M/s Dias Properties & Projects
48, Sativali, 401208
- Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 31.5%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · 48, Sativali
Area guide
What it's like to buy in Sativali
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The western line's volume market — dense affordable towers past Mira Road.
- Growth drivers:
- Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
- Who buys here:
- Budget-first buyers who commute the western line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P99000007801
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2022originally June 2021
- Construction
- 31.5% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Sativali compares.
In Sativali
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.