High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2022, now proposed Feb 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Feb 2024) has passed with construction at 52.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2024 per the RERA filing.

Promoter

Builder profile

Builder
Rushikesh Bhaguji Zore

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000021595
Status
New
Stage
Certificate Signed
Possession
February 2024originally June 2022
Construction
52.7% complete
Units sold
0 of 0

Similar projects in Pushpak New

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pushpak New compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.