Under construction
DJ AMORE2
MahaRERA P51800048275High risk
359,360, MUMBAI, 400074
Post your property hereOwn or renting out a unit in DJ AMORE2? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MUMBAI come to you.
Mar 2026
Possession
58.5%
Built
0
Complaints
22
Units
High risk
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 58.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.
Area guide
What it's like to buy in MUMBAI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
DHIRAJ narayandas JADHWANI
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800048275
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026originally April 2025
- Construction
- 58.5% complete
- Units sold
- 6 of 22
Similar projects in MUMBAI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
MULUND MAHAVIRDHAM CO. OP. HOUSING SOC. LTD.
MUMBAI100% builtPoss. March 2027
OM SAKTHI CO.OP.HSG.SOC.LTD
MUMBAI100% builtPoss. September 2027
valera chsl
MUMBAI100% builtPoss. November 2021
REDEVELOPMENT OF MALAD MARUDHAR CHSL
MUMBAI100% builtPoss. January 2025
CHANDRA DARSHAN HEIGHTS
MUMBAI100% builtPoss. December 20231 complaint
NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.
MUMBAI99.1% builtPoss. October 2023
OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
MUMBAI90.9% builtPoss. March 2027
AURUS
MUMBAI90.9% builtPoss. March 2024
Keep exploring
Where this project sits, who built it, and how MUMBAI compares.
In MUMBAI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.