High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2024, now proposed Dec 2030 per the RERA filing.
Satellite view of this address

Where it is · 105/4/1, 105/4/2, Dnyansagar Magal Karyalay

Area guide

What it's like to buy in Dnyansagar Magal Karyalay

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Dattakrupa Associates

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Pravin Patil

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100014850
Status
New
Stage
Certificate Signed
Possession
December 2030originally December 2024
Construction
78.8% complete
Units sold
85 of 239

Keep exploring

Where this project sits, who built it, and how Dnyansagar Magal Karyalay compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.