- Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
- Possession delayed ~3 yrs. Originally promised Jun 2021, now proposed Sept 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 79.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2024 per the RERA filing.
Where it is · 1/817 819 820, Girgaon
Area guide
What it's like to buy in Girgaon
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Heritage chawl-and-wadi belt in cluster redevelopment mode.
- Growth drivers:
- Cluster redevelopment policy, Metro 3, Coastal Road.
- Who buys here:
- South-Bombay natives staying local in new towers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900008314
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2024originally June 2021
- Construction
- 79.5% complete
- Units sold
- 0 of 0
Similar projects in Girgaon
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Girgaon compares.
In Girgaon
The developer
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.