Meadows
1012 ,1/1016 ,1013, Girgaon, 400004
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~1 yr. Originally promised Mar 2027, now proposed Mar 2028 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2028 per the RERA filing.
Where it is · 1012 ,1/1016 ,1013, Girgaon
Area guide
What it's like to buy in Girgaon
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Heritage chawl-and-wadi belt in cluster redevelopment mode.
- Growth drivers:
- Cluster redevelopment policy, Metro 3, Coastal Road.
- Who buys here:
- South-Bombay natives staying local in new towers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51900052589
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2028originally March 2027
- Construction
- 73.6% complete
- Units sold
- 33 of 503
Similar projects in Girgaon
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Girgaon compares.
In Girgaon
The developer
Data sourced from the official MahaRERA portal; complaints last synced 26 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.