High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~5 yrs. Originally promised Jun 2022, now proposed Apr 2027 per the RERA filing.
  • 20 RERA complaints. 20 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · CTS 22A/10 PT 22A/11A PT, 22A/14 PT, Siddharth Nagar, Goregaon (West)

Area guide

What it's like to buy in Siddharth Nagar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
EKTA EVERGLADE HOMES PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Sameer Desai

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800000731
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally June 2022
Construction
94.5% complete
Units sold
182 of 227

Keep exploring

Where this project sits, who built it, and how Siddharth Nagar, Goregaon (West) compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.