Caution
  • Behind schedule. Possession is due Nov 2026 but construction is only at 45.5%.
Satellite view of this address

Where it is · 2498, BORIVALI EAST

Area guide

What it's like to buy in BORIVALI EAST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
EMPIRE REALTY

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
CHIRAG RAYANI

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800054561
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
45.5% complete
Units sold
7 of 43

Keep exploring

Where this project sits, who built it, and how BORIVALI EAST compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.