Eraville Phase I
181/9/2 181/1/1B/ 183/8, Sadesataranali Hadapsar, 411028
- Possession delayed ~4 yrs. Originally promised Jun 2021, now proposed Dec 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 70.7%.
Where it is · 181/9/2 181/1/1B/ 183/8, Sadesataranali Hadapsar
Area guide
What it's like to buy in Sadesataranali Hadapsar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100016089
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024originally June 2021
- Construction
- 70.7% complete
- Units sold
- 30 of 38
Keep exploring
Where this project sits, who built it, and how Sadesataranali Hadapsar compares.
In Sadesataranali Hadapsar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.