🏗️
Under construction
ESTRELLAA
MahaRERA P52100011138High risk
25/1/3, Haveli, 411048
Post your property hereOwn or renting out a unit in ESTRELLAA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Haveli come to you.
Apr 2028
Possession
58.2%
Built
4
Complaints
0
Units
High risk
- Possession delayed ~7 yrs. Originally promised Dec 2020, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address
Where it is · 25/1/3, Haveli
Promoter
Builder profile
NIRMAANN ENCON DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100011138
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2028originally December 2020
- Construction
- 58.2% complete
- Units sold
- 0 of 0
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Skyi Wild Woods Phase I
HaveliPoss. November 2027
Valley Vista
HaveliPoss. December 2018
Vintage City
HaveliPoss. October 2023
Lambodar Gold
HaveliPoss. December 2021
Emerald City
HaveliPoss. December 2021
7 Peace Villas
HaveliPoss. July 2019
Nivaan Medows
HaveliPoss. April 20273 complaints
NIVAAN MEADOWS
HaveliPoss. April 20279 complaints
Keep exploring
Where this project sits, who built it, and how Haveli compares.
In Haveli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.