Under construction

Evernest Empressa

MahaRERA P52100076897High risk

by Evernest Infracity LLP

169, 170P, 171, 172, 176, 177, 178, 179, 180, 181, 182(P), 186, 187, 188, 189(P), 192(P), OPP BUDDH VIHAR, 411033

Official record
Sept 2027
Possession
39.2%
Built
0
Complaints
26
Units
High risk
  • Behind schedule. Possession is due Sept 2027 but construction is only at 39.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Promoter

Builder profile

Builder
Evernest Infracity LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
RAHUL KALBHOR

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100076897
Status
New
Stage
Certificate Signed
Possession
September 2027originally May 2027
Construction
39.2% complete
Units sold
9 of 26