High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Satellite view of this address

Where it is · 110 1A/1B, Thane

Promoter

Builder profile

Builder
EWAR CONSTRUCTIONS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700014636
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.