Under construction
Feriha Heights
MahaRERA P51600055909High risk
Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar, 422007
Post your property hereOwn or renting out a unit in Feriha Heights? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Wadala, Shiwar come to you.
Jul 2027
Possession
45.5%
Built
0
Complaints
28
Units
High risk
- Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Jul 2027 per the RERA filing.
- Behind schedule. Possession is due Jul 2027 but construction is only at 45.5%.
Satellite view of this address
Where it is · Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar
Promoter
Builder profile
Aroma Developers
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51600055909
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2027originally March 2026
- Construction
- 45.5% complete
- Units sold
- 13 of 28