🏗️
Under construction

Feriha Heights

MahaRERA P51600055909High risk

by Aroma Developers

Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar, 422007

Official record
Mar 2027
Possession
49.1%
Built
0
Complaints
28
Units
High risk
  • Behind schedule. Possession is due Mar 2027 but construction is only at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Satellite view of this address

Where it is · Plot No- 20+21, Survey No- 113/3/11 to 16/21 to 23, Wadala, Shiwar

Promoter

Builder profile

Builder
Aroma Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600055909
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
49.1% complete
Units sold
13 of 28

Keep exploring

Where this project sits, who built it, and how Wadala, Shiwar compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.