Under construction
FESTIVE RESIDENCY
MahaRERA P52100016432High risk
S.NO.189/1/1/3P, TALUKA MULASHI, 411057
Post your property hereOwn or renting out a unit in FESTIVE RESIDENCY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TALUKA MULASHI come to you.
Dec 2027
Possession
74.1%
Built
3
Complaints
76
Units
High risk
- Possession delayed ~5 yrs. Originally promised Mar 2023, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address
Where it is · S.NO.189/1/1/3P, TALUKA MULASHI
Promoter
Builder profile
SAMRUDDHI DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100016432
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally March 2023
- Construction
- 74.1% complete
- Units sold
- 31 of 76
Keep exploring
Where this project sits, who built it, and how TALUKA MULASHI compares.
In TALUKA MULASHI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 25 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.