High risk
  • Possession delayed ~5 yrs. Originally promised Mar 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · S.NO.189/1/1/3P, TALUKA MULASHI

Promoter

Builder profile

Builder
SAMRUDDHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100016432
Status
New
Stage
Certificate Signed
Possession
December 2027originally March 2023
Construction
74.1% complete
Units sold
31 of 76

Keep exploring

Where this project sits, who built it, and how TALUKA MULASHI compares.