Flamingo city of Valley Phase 1
by FLAMINGO CONSTRUCTIONS PRIVATE LIMITED
219/1A 219/1B 219/2 255/1 124/1 194/1 2 4 5 6 195/1 2 3, Mulshi, 411042
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
Where it is · 219/1A 219/1B 219/2 255/1 124/1 194/1 2 4 5 6 195/1 2 3, Mulshi
Area guide
What it's like to buy in Mulshi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100014608
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 21.6% complete
- Units sold
- 0 of 214
Similar projects in Mulshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Mulshi compares.
In Mulshi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.