Under construction

GAGAN UNO

MahaRERA P52100001400High risk

by GAGAN ACE DEVLOPERS

PLOT NO 4-8, FINAL PLOT NO 153, TPS-1, CTS NO38,38/1,38/2,39,41, Sangamwadi, 411001

Official record
Dec 2027
Possession
80.9%
Built
0
Complaints
67
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO 4-8, FINAL PLOT NO 153, TPS-1, CTS NO38,38/1,38/2,39,41, Sangamwadi

Area guide

What it's like to buy in Sangamwadi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
GAGAN ACE DEVLOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100001400
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2019
Construction
80.9% complete
Units sold
47 of 67

Similar projects in Sangamwadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Sangamwadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.