- Possession delayed ~1 yr. Originally promised Jun 2024, now proposed Aug 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 78.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2025 per the RERA filing.
Where it is · 81, Vile Parle West
Area guide
What it's like to buy in Vile Parle West
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Beachside bungalows and low-rise society redevelopments.
- Growth drivers:
- Beach frontage, airport access, redevelopment of ageing societies.
- Who buys here:
- Established business families, film industry.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51800050876
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2025originally June 2024
- Construction
- 78.2% complete
- Units sold
- 21 of 44
Keep exploring
Where this project sits, who built it, and how Vile Parle West compares.
In Vile Parle West
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.