Under construction

GALAXY PRIME

MahaRERA P52000054907High risk

by GALAXY BUILDCON

257, Sector 24 at Pushpak Node, Ulwe, Sector 24, Pushpak Node, 410206

Official record
Dec 2026
Possession
34.5%
Built
0
Complaints
38
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 34.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 257, Sector 24 at Pushpak Node, Ulwe, Sector 24, Pushpak Node

Area guide

What it's like to buy in Sector 24

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
GALAXY BUILDCON

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000054907
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
34.5% complete
Units sold
10 of 38

Keep exploring

Where this project sits, who built it, and how Sector 24, Pushpak Node compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.