Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 93%.
Satellite view of this address

Where it is · PLOT NO.25, Thane

Promoter

Builder profile

Builder
SHRI GAMI INFOTECH PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700013200
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
93% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.