High risk
  • Possession delayed ~2 yrs. Originally promised Oct 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 69.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address

Where it is · 452 1 1, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Vinayak Pandharinath Bhongale

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Anuradha Govardhan

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100047726
Status
New
Stage
Certificate Signed
Possession
June 2026originally October 2024
Construction
69.5% complete
Units sold
11 of 13

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.