High risk
  • Possession delayed ~1 yr. Originally promised Sept 2019, now proposed Mar 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 42.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2021 per the RERA filing.
Satellite view of this address

Where it is · SR NO43/1/1/5A/1, PUNE

Area guide

What it's like to buy in PUNE

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Parel / Dadar EastPremium

Mill-land towers around Maharashtra's busiest rail junction.

Growth drivers:
Hospital cluster jobs, central location, mill plot launches.
Who buys here:
South-Bombay workers wanting new construction.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
V.N.D CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004383
Status
Ongoing
Stage
Certificate Signed
Possession
March 2021originally September 2019
Construction
42.7% complete
Units sold
0 of 0

Similar projects in PUNE

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how PUNE compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.