High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Ganesh Paradise Phase I

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100024550
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2025
Construction
90.4% complete
Units sold
172 of 238

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.