High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2023, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 58.7%.
Satellite view of this address

Where it is · 27, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHREE VENKATESHWARA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800021114
Status
New
Stage
Certificate Signed
Possession
July 2026originally July 2023
Construction
58.7% complete
Units sold
3 of 38

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.