  • Possession delayed ~3 yrs. Originally promised Mar 2020, now proposed Mar 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 65.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. - 9, Bhiwandi

Promoter

Builder profile

Builder
TELE BUILD CONSTRUCTION PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700005592
Status
Ongoing
Stage
Certificate Signed
Possession
March 2023originally March 2020
Construction
65.5% complete
Units sold
0 of 0

Similar projects in Bhiwandi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Bhiwandi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.