High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Aug 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 81.6%.
Satellite view of this address

Where it is · Survey No. 20 hIssa No. 9, Kalyan

Promoter

Builder profile

Builder
Kanubhai Mohanbhai Lakkad

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700009950
Status
Ongoing
Stage
Certificate Signed
Possession
August 2024originally December 2019
Construction
81.6% complete
Units sold
0 of 0

Similar projects in Kalyan

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kalyan compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.