High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 93/A/Part, Plot No 82 And 83, Near DNC School

Area guide

What it's like to buy in Near DNC School

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NEELPADMA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Mr. Shirish G. Nachane

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700032519
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
43.4% complete
Units sold
10 of 28

Keep exploring

Where this project sits, who built it, and how Near DNC School compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.