High risk
  • Possession date passed. The proposed possession date (Nov 2023) has passed with construction at 0%.

Promoter

Builder profile

Builder
SANJAY JANARDAN GANDHI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000027258
Status
New
Stage
Certificate Signed
Possession
November 2023
Construction
0% complete
Units sold
0 of 0

Similar projects in ALIBAG

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how ALIBAG compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.