High risk
  • Litigation pending (12). MahaRERA's litigation disclosure lists 12 pending cases against this project.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · S NO 91/1 Part, Mawal

Area guide

What it's like to buy in Mawal

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Gini Citicorp Realty LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
CUBIX Architects Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100048895
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
73.6% complete
Units sold
180 of 180

Similar projects in Mawal

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mawal compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.