Under construction

Giri Darshan Apartment

MahaRERA P52100011639High risk

by Concept Townships & Estate Developers Pvt Ltd

CTS No 751/ Survey No 474/1, 476, 480/1B, 480/2B, 480/3A/ Plot No 41, Talegaon Dabhade (M Cl), 410507

Official record
Dec 2019
Possession
54.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 54.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.
Satellite view of this address

Where it is · CTS No 751/ Survey No 474/1, 476, 480/1B, 480/2B, 480/3A/ Plot No 41, Talegaon Dabhade (M Cl)

Promoter

Builder profile

Builder
Concept Townships & Estate Developers Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100011639
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
54.5% complete
Units sold
0 of 0

Similar projects in Talegaon Dabhade (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Talegaon Dabhade (M Cl) compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.