GODREJ BOULEVARD
by Manjari Housing Projects LLP
Sector R7 - Gat Nos 124 part, 125 part, 127 part and 137 part, Manjri Khurd, 412307
- Litigation pending (10). MahaRERA's litigation disclosure lists 10 pending cases against this project.
- Mortgaged to a lender (₹230 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹230 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 81.8%.
Where it is · Sector R7 - Gat Nos 124 part, 125 part, 127 part and 137 part, Manjri Khurd
Area guide
What it's like to buy in Manjri Khurd
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100024616
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2025
- Construction
- 81.8% complete
- Units sold
- 770 of 780
Keep exploring
Where this project sits, who built it, and how Manjri Khurd compares.
In Manjri Khurd
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.