Godrej Central
by Godrej Landmark Redevelopers Private Limited
CTS 49/pt, 56, 54, 45, 58/pt, Kurla, 400071
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- 15 RERA complaints. 15 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 89.1%.
Where it is · CTS 49/pt, 56, 54, 45, 58/pt, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800001107
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2021
- Construction
- 89.1% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.