Under construction

Godrej Emerald Thane

MahaRERA P51700000120High risk

by Godrej Greenview Housing Private Limited

91/1/1A 91/2A 102/1,2B,2C,3Bpt 103/3Apt 103/4pt 103/5B/2 109/30/1Bpt 109/30/4A 109/33,34 196, Thane, 400615

Official record
Jun 2026
Possession
99.6%
Built
29
Complaints
1,183
Units
High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Mortgaged to a lender (₹50 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹50 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • 14 appeals at MahaREAT. 14 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Jun 2026 per the RERA filing.
  • 29 RERA complaints. 29 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 99.6%.
Satellite view of this address

Where it is · 91/1/1A 91/2A 102/1,2B,2C,3Bpt 103/3Apt 103/4pt 103/5B/2 109/30/1Bpt 109/30/4A 109/33,34 196, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Godrej Greenview Housing Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700000120
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2024
Construction
99.6% complete
Units sold
1151 of 1183

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.