Official record
Mar 2028
Possession
80%
Built
69
Complaints
1,210
Units
High risk
  • Litigation pending (8). MahaRERA's litigation disclosure lists 8 pending cases against this project.
  • Mortgaged to a lender (₹250 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹250 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • 18 appeals at MahaREAT. 18 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Mar 2024, now proposed Mar 2028 per the RERA filing.
  • 69 RERA complaints. 69 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · Plot 1 of Survey nos 11/1A, 12/1, 12/2/1, 12/2/2, 12/2/3, 13/1B part and 13/2, Village Mamurdi, Mamurdi

Area guide

What it's like to buy in Mamurdi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Godrej Skyline Developers Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Studio 30 Architects and Planners

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100019639
Status
New
Stage
Certificate Signed
Possession
March 2028originally March 2024
Construction
80% complete
Units sold
1193 of 1210

Similar projects in Mamurdi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mamurdi compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.