High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2021, now proposed Dec 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 78.2%.
Satellite view of this address

Where it is · S NO 12 HISSA NO 2, SHELU

Promoter

Builder profile

Builder
SHREEJI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000009607
Status
Ongoing
Stage
Certificate Signed
Possession
December 2025originally June 2021
Construction
78.2% complete
Units sold
0 of 0

Similar projects in SHELU

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SHELU compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.