Under construction

Gold Crest

MahaRERA P51700031489High risk

by Jay Ganesh Developers

City S No 5031 to 5051, 5548 to 5565, 5695 to 5718, Ayre Goan, 421201

Official record
Sept 2027
Possession
44.8%
Built
0
Complaints
202
Units
High risk
  • Possession delayed ~2 yrs. Originally promised May 2025, now proposed Sept 2027 per the RERA filing.
  • Behind schedule. Possession is due Sept 2027 but construction is only at 44.8%.

Area guide

What it's like to buy in Ayre Goan

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Jay Ganesh Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700031489
Status
New
Stage
Certificate Signed
Possession
September 2027originally May 2025
Construction
44.8% complete
Units sold
106 of 202

Keep exploring

Where this project sits, who built it, and how Ayre Goan compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.