Under construction

GOLDEN VISTA

MahaRERA P51800078953High risk

by GOLDEN VISTA

CTS NO 5608/1,5608/A (pt) & 5621C, Andheri, 400098

Official record
Apr 2030
Possession
27.3%
Built
0
Complaints
172
Units
High risk
  • Mortgaged to a lender (₹45 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹45 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
Satellite view of this address

Where it is · CTS NO 5608/1,5608/A (pt) & 5621C, Andheri

Promoter

Builder profile

Builder
GOLDEN VISTA

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SULTAN CHAMBYAL

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800078953
Status
New
Stage
Certificate Signed
Possession
April 2030originally December 2029
Construction
27.3% complete
Units sold
52 of 172

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 27 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.