Under construction

Govind Nagar SRA CHS Ltd.

MahaRERA P51800010475High risk

by Drishti Developers II

CTS No. 13/38/4, 13/1 part, 583 part, mahakali, 400093

Official record
Sept 2025
Possession
98.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2022, now proposed Sept 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 98.7%.
Satellite view of this address

Where it is · CTS No. 13/38/4, 13/1 part, 583 part, mahakali

Area guide

What it's like to buy in mahakali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Drishti Developers II

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800010475
Status
Ongoing
Stage
Certificate Signed
Possession
September 2025originally September 2022
Construction
98.7% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how mahakali compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.