High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2021, now proposed Oct 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2022) has passed with construction at 38.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2022 per the RERA filing.
Satellite view of this address

Where it is · 6260,6263, PCMC(DANGE CHOWK) CHINCHWAD

Promoter

Builder profile

Builder
KONARK ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100009837
Status
Ongoing
Stage
Certificate Signed
Possession
October 2022originally April 2021
Construction
38.2% complete
Units sold
0 of 0