Under construction

Grandbay

MahaRERA P52100020969High risk

by S K ASSOCIATES

S.No.273 2,CTS No. 1023B 58,1023B 59,1023B 60, Shirur, 412210

Official record
Jun 2023
Possession
72.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 72.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Promoter

Builder profile

Builder
S K ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100020969
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
72.7% complete
Units sold
0 of 0

Similar projects in Shirur

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Shirur compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.