Under construction

GREEN LEAF

MahaRERA P52100014561High risk

by M/S KWALITY DEVELOPERS

NEW CTS NO 747/17 OLD CTS NO 779 AND OLD SURVEY NO 495/1/A-1 ALLOTTED PLOT NO 20, BHAVANI PETH, 411011

Official record
Dec 2020
Possession
59.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 59.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Satellite view of this address

Where it is · NEW CTS NO 747/17 OLD CTS NO 779 AND OLD SURVEY NO 495/1/A-1 ALLOTTED PLOT NO 20, BHAVANI PETH

Promoter

Builder profile

Builder
M/S KWALITY DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100014561
Status
New
Stage
Certificate Signed
Possession
December 2020originally December 2018
Construction
59.1% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how BHAVANI PETH compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.