High risk
  • Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 78.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2024 per the RERA filing.

Promoter

Builder profile

Builder
AQUBE INFRASTRUCTURES AND DEVELOPERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50500029037
Status
New
Stage
Certificate Signed
Possession
September 2024
Construction
78.8% complete
Units sold
0 of 0