High risk
  • Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 76.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2019 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 276, SINDHI SOCIETY

Area guide

What it's like to buy in SINDHI SOCIETY

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SANJAY JUMANI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800012498
Status
New
Stage
Certificate Signed
Possession
July 2019
Construction
76.4% complete
Units sold
0 of 0

Similar projects in SINDHI SOCIETY

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SINDHI SOCIETY compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.