Under construction

GUNDECHA REXON SUITES PHASE 1

MahaRERA P51800034503Caution

by ANAYA INFRASTRUCTURE PVT LTD

CTS NO 1383, 1385A, 1385B & 918A, Borivali, 400062

Official record
Oct 2028
Possession
37.3%
Built
0
Complaints
230
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Mar 2026, now proposed Oct 2028 per the RERA filing.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ANAYA INFRASTRUCTURE PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800034503
Status
New
Stage
Certificate Signed
Possession
October 2028originally March 2026
Construction
37.3% complete
Units sold
25 of 230

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.