High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 66.4%.
Satellite view of this address

Where it is · S NO 5, Pune (M Corp.)

Area guide

What it's like to buy in Pune (M Corp.)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Lower Parel / WorliUltra-luxury

Mill-land skyscraper district — corporate HQs, five-stars and sea-view towers.

Growth drivers:
Coastal Road and Sea Link access, premium office stock, Worli sea-face cachet.
Who buys here:
CXOs, HNIs and investors chasing trophy addresses.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
GURUDATTA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100014253
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
66.4% complete
Units sold
0 of 0

Similar projects in Pune (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pune (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.