Under construction
Gurudeep Apartment
MahaRERA P51600053395High risk
SN.37/1/2/1 PLOT5, NASHIK ROAD, 422101
Post your property hereOwn or renting out a unit in Gurudeep Apartment? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in NASHIK ROAD come to you.
Jun 2026
Possession
84.1%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 84.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address
Where it is · SN.37/1/2/1 PLOT5, NASHIK ROAD
Promoter
Builder profile
ANUP BUILDCON
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
SURESH PATEL
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P51600053395
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 84.1% complete
- Units sold
- 0 of 0
Similar projects in NASHIK ROAD
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
TRAMBAK SANKUL
NASHIK ROADPoss. July 2029
SHRI GANESH RESIDENCY
NASHIK ROAD100% builtPoss. September 2023
MALHAR APARTMENT
NASHIK ROAD100% builtPoss. August 2022
OM PRAGATI
NASHIK ROAD100% builtPoss. June 2024
SHREE HARI SHRUSTI
NASHIK ROAD100% builtPoss. July 2024
CHANDRA TARA
NASHIK ROAD100% builtPoss. October 2024
SAI APARTMENT
NASHIK ROAD100% builtPoss. January 2025
AJANTA NAGARI CO OP HSG SOCIETY
NASHIK ROAD100% builtPoss. August 2026
Keep exploring
Where this project sits, who built it, and how NASHIK ROAD compares.
The developer