High risk
  • Mortgaged to a lender. MahaRERA's financial encumbrance declaration shows this project is mortgaged to a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • 6 appeals at MahaREAT. 6 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~5 yrs. Originally promised Apr 2023, now proposed Dec 2027 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 123, Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
LOTUS LAKSHMINARAYAN HOMES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SHAPE CONSULTANT

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000015966
Status
New
Stage
Certificate Signed
Possession
December 2027originally April 2023
Construction
69.9% complete
Units sold
185 of 361

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.