High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2023, now proposed Dec 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · TIKA NO 22, CTS NO 5/2 AND 5/3, Vishnu Nagar

Area guide

What it's like to buy in Vishnu Nagar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Thane (Ghodbunder belt)Mid-income

A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Trimity Constructions

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
10 Folds Architects and Consultants

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700022306
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2023
Construction
60.5% complete
Units sold
23 of 48

Similar projects in Vishnu Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vishnu Nagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.